The Integrated Public Transport System () is the public transport system in Bogotá, the capital and largest city of Colombia. It integrates bus rapid transit (BRT), bus and gondola lift services in the metropolitan area of Bogotá.

History

Beginnings and tender

During the 2007 campaign for the election of mayor of the city, the candidate Samuel Moreno Rojas had as a campaign proposal, in addition to the construction of phase III of TransMilenio and the Bogotá Metro, the implementation of an ambitious project whose mission was to order and integrate the traditional public transport system with TransMilenio.

Integrated Public Transport System (Bogotá)

In October 2009 and then as mayor, Moreno announced the start of the tender of the 13 zones in which the city was divided and to which an operator and the System of Collection and Control of Information (Sirci) would be assigned. On December 18 of that same year, Javier Hernández was appointed as manager of the SITP, a position he would occupy until March 2012.

Integrated Public Transport System (Bogotá)

During the first four days of March 2010, the Moreno administration suffered one of the biggest crises with a transporters strike demanded their inclusion in the SITP and managing to paralyze the city. Finally, and after extensive negotiations, Moreno and the transporters agreed to include them among the bidding companies and scrap projects for the very old buses that could not enter the system, which implied a delay in the assignment of the operators. In November, all that was needed was the tender for an area.

Integrated Public Transport System (Bogotá)

Delays

In 2011, with all the operators assigned and waiting to sign contracts, a judge of the republic revoked the bidding process for the award of the Sirci, arguing that the process had not received sufficient attention by the control entities and that they were still missing key points to be defined in the contract that would be signed by the winning company. This delay, together with the outbreak of a corruption case of the hiring involving Mayor Moreno and senior officials of the mayor's office, would be the main reasons in the delay of the implementation of the system, which lasts until today. On June 16 of this year, it was finally possible to award the collection of fares for the system, calculated at 2.7 billion pesos per year, to the company Recaudo Bogotá S.A. with a 16-year contract.

In spite of the promises of the manager of TransMilenio during that time, Fernando Páez, that the SITP would begin operations in December 2011, due to delays in the delivery of phase III of said system, Paéz himself had to say in September that it would not be until May 2012 when the gradual implementation of routes could be initiated. On the other hand, already from this time, a problem was noticed about people's ignorance of the system and lack of pedagogy. Finally, on December 31 and after three years of delay, the mayor in charge of Bogotá, Clara López, received the works of Phase III of TransMilenio, which meant a great advance in unlocking the implementation of the system.

Start of operation

In January 2012, with the entry of Gustavo Petro to the mayor's office and a new cabinet, it was reported that the works of phase III were incomplete and that there would still be time until the start of their operations. For this reason, it was announced that the SITP could start until June 9 of the same year. In addition, the first financial problems of the Coobus SAS operator began to be reported. who was in charge of Calle 26 and the Fontibón zone. During May of the same year, tests were begun on Phase III of TransMilenio, with satisfactory results. Despite this, the administration was unable to comply with the date given for the start of operations on the Calle 26 and Carrera 10 trunk lines.

On June 30, despite pressure from various sectors, Gobernación and El Dorado Portal stations began operation on Calle 26 for free due to delays in the implementation of the fare collection system. Finally, with a fare adjustment from July 22, the operation is gradually implemented in phase III. Immediately, another problem of the system surfaced and it is the use of two different cards, one for phase I and II and another for SITP and phase III.

Although it had been said that the first urban route would begin to operate in August, it was until September 22 that two urban routes began operating in pedagogical mode. The route of one of them is from El Dorado Airport to the Andino Shopping Center and the other from Altos de Zuque to Paloquemao. Complementary routes began operation on November 1, 2012, special routes on December 1, 2012, and the traditional bus system was formally abolished on September 16, 2016, thus integrating public transport in Bogotá.