ArcelorMittal South Africa is part of the steel company Arcelor-Mittal. The company was originally Iscor Ltd., a South African parastatal steel company. It was founded in 1928 and was first listed on the JSE Securities Exchange in 1989.
History
Establishment of the company
Hendrik van der Bijl, one of the most influential South Africans of the twentieth century, together with Dr. Fredrik "Frikkie" Meyer, (a student of Albert Einstein while studying in Berlin), and others, were the main driving force behind the establishment of the South African Iron and Steel Industrial Corp. (Iscor).
Iscor, with its first works in Pretoria built by the German Demag, was established as a state company in terms of the Iron and Steel Industry Act, No. 11 of 1928. The objectives of establishing the company were to produce iron and a range of steel products, and to create employment opportunities.
Production at the Pretoria plant started in 1934. On 4 April 1934 the first steel was tapped from the open-hearth furnace at the Pretoria Works. Wartime needs for steel and the local manufacture of numerous necessities brought about a sharp increase in demand. Iscor had to expand, and the Pretoria works had reached their limit of growth.
In 1941 Dr. van der Bijl and his fellow directors decided that expansion in a new area had become necessary. The idea of a new steelworks in Vereeniging was revived. For the immediate war needs it was decided to begin by building a plate rolling mill planned in such a way that it could later form part of a large integrated steelworks.
The situation of the terrain along the Vaal River west of Vereeniging made it ideal for development. There was sufficient slope for drainage towards the river and the area was downstream from the Rand Water Board's pumping station intake. The heavy industries could be suitably sited on relatively high ground in a position where the prevailing winds would minimise the dangers of pollution. Dr. van der Bijl convinced the directors of Iscor that the area beside the Vaal River was the obvious site for Iscor's new steelworks.
After the discovery of iron ore at Thabazimbi, the African Metals Corp. (Amcor) was established near Vereeniging in 1937. The erection of the Plate Mill was completed in 1943 and went into production the same year. Iscor started trading in 1947.
Directly after World War II, it was decided to build a fully integrated steel works at Vanderbijlpark, and a start was made on this early in 1947. On 4 October 1952 the Vanderbijlpark Works officially opened by His Excellency the Governor General, Dr E.G. Jansen. Several of the new production units started up in 1953, followed by major expansion schemes in 1956, 1960. From 1964 to 1969 a second development phase started at Vanderbijlpark Works. Large extensions were added; older plants modernised to supply higher quality and value-added products such as electrolytic tinplate for the canning and beverage industries.
On 17 May 1969 the South African Government decided that Iscor's third fully integrated steelworks be erected at Newcastle. The main factor leading to this selection was to decentralise industry away from the Witwatersrand complex and to promote industrial development in Natal, the best watered province of South Africa. Newcastle, as a border area with an adequate supply of labour, and with the Amcor ironworks that could be taken over to save on initial capital costs as well as to provide an outlet for the iron which was at that time being exported to Yawata in Japan ( the contract for which was to expire shortly), was therefore chosen.
Further factors were that Newcastle was situated on main rail and road routes between Johannesburg and Durban, essential services such as water and electricity were already well catered for, and the town had a basic established infrastructure with a settled community. While ore would have to be transported 1 000 km from Sishen, coking coal was available from nearby and the overall economics were favourable. It was decided that both profile and flat products would be catered for in a plant with an ultimate capacity of 8 million tons per annum of liquid steel. Subsequent changes in steel markets has meant that extension to flat products has been delayed indefinitely and the current capacity is about 2,00 million tons of liquid steel.