The Neckarelz–Osterburken railway is a 30.9 km long railway line in the north of the German state of Baden-Württemberg, which connects the Neckar and the Bauland along the edge of the Odenwald. It was opened in 1866 as part of the Odenwald Railway (Baden) (Odenwaldbahn) between Heidelberg and Würzburg. It has been upgraded to form an entirely double-track and electrified main line railway. It was an east–west axis for German long-distance transport until 1945. Since 2003 passenger services on it have been operated by the Rhine-Neckar S-Bahn. The Neckarelz–Mosbach section has also been served by the Heilbronn Stadtbahn since 2014.

Route

The track today starts at Mosbach-Neckarelz station, where the Neckar Valley Railway branches off. Until about 1960 there was a connecting curve from Mosbach to Hochhausen on the Neckar Valley Railway. Until 1895, the old route of the Odenwald Railway from Obrigheim connected before the line reaches the current site of the Mosbach station, which was built in 1997. The line leaves the Neckar Valley, running along the Elz and Auerbach rivers, to enter an area of karst landscape known as the Bauland. A loop of the Elz is shortened by the Dallau tunnel.

Neckarelz–Osterburken railway

The line tunnels under the watershed between the Elz and the Jagst through Schefflenz Tunnel to reach the Schefflenz valley. It runs through Eicholzheim tunnel to the Seckach valley and in Seckach connects with the Madonnenland Railway to Miltenberg. The line runs through Adelsheim tunnel to the Kirnau valley, where it connects with the Franconia Railway in Osterburken.

Neckarelz–Osterburken railway

The line runs parallel with federal Highway B 27 from Neckarelz to Auerbach and then the B 292 to Oberschefflenz.

Neckarelz–Osterburken railway

History

The Neckarelz–Osterburken railway was developed as part of the Odenwald Railway from Heidelberg to Würzburg, which was completed on 1 November 1866. Heidelberg was connected to the railway network by the Grand Duchy of Baden State Railway’s Rhine Valley Railway in 1840. In 1854 the Ludwig's Western Railway was opened from Bamberg in Bavaria to the Hessian border near Kahl am Main through Würzburg. Both Bavaria and Baden saw reasons to build a railway line between Heidelberg and Würzburg: the government of Baden sought a continuation of its main line to the north east and the Bavarian king, Maximilian II, sought a connection with the Palatinate, then a geographically separate part of Bavaria.

The shortest route between the two cities would have run via Eberbach, Mudau and Miltenberg through Hesse, which saw this route as being opposed to its own interests. Instead, after a review of 45 alternative routes and lengthy negotiations, a decision was taken to build a line through Meckenheim, Mosbach, Osterburken and Lauda. This had the advantage for Baden that the line opened up the Baden Bauland and that it could operate entirely within Baden, as it only reached Bavaria at the end of the line. The disadvantages that had to be taken into account were an unfavourable topography and a route that was 25 km longer than the shortest route. A treaty adopting the agreed route was signed between the two countries on 27 January 1862. The Mosbach–Osterburken section was put into operation on 25 August 1866.

Baden State Railways era (1866-1920) Four years after the start of operations on the line, the Franco-Prussian War of 1870/1871 used its capacity in full. With Baden entering the war on 16 July 1870 the line was part of the military infrastructure. From 28 July 1870 until 15 October 1871 it was a military line. There was one pair of civilian passenger trains each day; all other capacity was made available for military traffic.

After the end of the war, Baden, Hesse and Württemberg agreed to the construction of the Neckar Valley Railway from Neckargemünd via Neckarelz to Jagstfeld and on 24 May 1879 rail traffic between Heidelberg and Mosbach followed the Neckar and avoided the topographically difficult Odenwald Railway. Therefore, a relocation of Neckarelz station was necessary: the old station was built at the end of the bridge over the Neckar on the Odenwald Railway, the new station was built on the new line along the Neckar river. From the new station two curves were built to Mosbach and to the Meckenheim line. The old Odenwald Railway between the old railway station and Mosbach remained in place, but in 1895 it was considered unnecessary and was abandoned.

Duplication of the line together with the Neckar Valley Railway between Neckargemünd and Neckarelz began in 1904 and was completed on 29 April 1906.