=Trench Method.=--Two distinct methods of placing the gravel are in general use, known as the trench method and the surface or feather edge method respectively. The method to adopt for any particular road will depend largely on certain conditions that will be explained later.
In the trench method, a trench of the proper width and depth for receiving the gravel is excavated in the earth road surface and the gravel is placed therein.
The trench is formed by plowing a few furrows and scraping out the loosened earth with a blade grader. The loose material is generally moved out laterally to build up earth berms or "shoulders" alongside the gravel. Into this trench the gravel is dumped in the proper quantity to give the required thickness after being compacted.
The greatest care must be exercised in spreading the gravel to eliminate unevenness where the loads were deposited. An ordinary blade grader is one of the best and most economical implements to use for spreading the gravel. When the gravel has been deposited in the trench for a distance of a thousand feet or more, the spreading is accomplished by dragging the surface repeatedly with the blade grader, the work being continued until all waviness disappears. The gravel is then thoroughly and repeatedly harrowed with a heavy stiff tooth harrow to mix thoroughly the fine and coarse gravel so as to produce as nearly a uniform mixture as may be. The gravel is then finally smoothed with the blade grader.
The gravel may be compacted by rolling or may be allowed to pack from the action of traffic. The former is greatly to be preferred where practicable. The rolling is performed with a three-wheeled self-propelled roller weighing about 8 tons and must be done while the gravel is wet. Generally a sprinkling wagon is used to wet down the gravel, but advantage is always taken of rains to facilitate the work. The gravel must be spread in layers not over 5 or 6 inches thick to get the desired results, which means that for an ordinary gravel road about 10 inches thick, the gravel will be placed in two layers of about equal thickness, each of which will be rolled.
The gravel will compact slowly even if it is not rolled, but generally does not become stable until the material is thoroughly soaked by rains. Then it will begin to pack, but will become badly rutted and uneven during the process. During this period the surface must be kept smooth by means of the blade grader. The drag does not suffice for this purpose, tending to accentuate the unevenness rather than to correct it.