These 940 days include practically all the time elapsed, except Sundays and such few holidays as were observed. For some of this time, work was being carried on at only one or two points; the time, therefore, represents practically the total possible working time during the period covered.

_Progress at Weehawken._--At Weehawken the total number of days worked was 763, divided as follows:

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 — Part 18

186 days in timbered section, about 426 ft., an average rate of 2.3 ft. per day in each tunnel;

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 — Part 18

176 days in hard sandstone, about 563 ft., an average rate of 3.2 ft. per day in each tunnel;

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 — Part 18

112 days in hard trap, about 267 ft., an average rate of 2.4 ft. per day in each tunnel;

289 days in ordinary trap, about 1,316 ft., an average rate of 4.55 ft. per day in each tunnel.

_Progress at Central Shaft._--At Central Shaft the average length driven per day in each of the four headings is shown by Table 4.

-----------+----------------+-----------------+---------------------+ Location. | Number of days | Total length of | Average length of | | worked. | heading, in | heading driven per | | | feet. | day worked, in feet.| -----------+----------------+-----------------+---------------------+ | | | | N.E. | 227 | 446 | 1.96 | S.E. | 168 | 346 | 2.06 | N.W. | 272 | 768 | 2.82 | S.W. | 234 | 698 | 2.98 | -----------+----------------+-----------------+---------------------+

_Progress at Hackensack._--At Hackensack the total number of days worked on the tunnels proper, all in trap rock (omitting the cut and cover) was about 792, divided as shown in Table 5.

------------------------------+----------+----------+----------+ |Number of | | Average | Location. | days | Advance. | advance | | worked. | | per day. | ------------------------------+----------+----------+----------+ Station 323 to Central Shaft | | | | headings | 492 | 1,450 | 4.5 | Bench and enlargement of | 159 | { 1,150* | 7.2* | Central Shaft headings | | { 906† | 5.7† | Central Shaft headings to | | | | Weehawken headings | 141 | 620 | 4.4 | ------------------------------+----------+----------+----------+

[† Equivalent linear feet of full section tunnel.]

The best month’s work in each location was as follows, the actual yardage excavated and paid for being reduced to equivalent linear feet of full section. The tunnels were generally taken out to full section, except for a small amount left in the bottom, which latter reduced the equivalent linear feet of full section to about 95% of the actual advance at the face.