The çãEmborcação Dam, also known as Theodomiro Santiago, is an embankment dam on the Paranaíba River near Araguari in Minas Gerais, Brazil. It was constructed for hydroelectric power production and flood control.

Background

Feasibility studies for the dam occurred in 1971 and in June 1977, construction on the dam began. In August 1981, the dam began to impound the reservoir and the first generator became operation in 1982, the last in 1983. The dam was inaugurated in 1983 by Brazilian president João Batista Figueiredo.

Emborcação Dam

Dam

The dam is long and tall and withholds a reservoir with a capacity of and surface area of .

Emborcação Dam

Emborcação Hydroelectric Power Plant

The dam's power plant contains four generators powered by Francis turbines for a total installed capacity of .