The operations of taking out the “bench” were carried on at a distance of about 170 yards back from the fore-breast. This was effected by first drilling six holes 7 feet deep; two of these were each about 4 feet from the face of the bench and close to the side of the tunnel, whilst two others were each 4 feet behind these first holes, and the remaining two holes were 8 feet from the face, 8 feet from the sides of the tunnel, and 8 feet from each other. These were fired simultaneously, the result being to lower the bench about 7 feet throughout the full width of the tunnel. At a safe distance beyond this first bench cut, the same operations were carried on by another gang of men, whereby the bench was lowered to the floor of the tunnel, the full area of 24 feet in width by 22 in height being thus completed. The rock was a moderately tough granite.

_The Musconetcong Tunnel._--The heading of the tunnel, shown on Plate XII., like that of the Hoosac, was driven to the full width of the tunnel. It is clear from theoretical considerations, and experience has confirmed the conclusions, that the method of taking, with machine drills, the whole width of the excavation at once conduces to rapidity of advance, and to economy of explosive. In the example under consideration, three tram lines were laid up to the face. The carriages carrying the drills were run upon the two outside lines. These carriages were simply stout frameworks of oak, each having in front three horizontal iron bars, on which the drills were clamped in a way that ensured easy lateral and vertical motion. After the firing of a blast, all hands were set to shovel the dislodged rock into the middle between the machine lines for the purpose of clearing the latter as soon as possible to make way for the machines to be brought up for the next boring. The lines being thus cleared, drilling was recommenced, and the broken rock removed in wagons upon the centre line of rails. The heading being 26 feet wide, there was ample room, and, a convenient system of switching having been adopted, no delay was occasioned by a want of wagons.

Rock Blasting — Part 77

The system followed was that of centre cuts, and subsequent squaring up. It consists in first blasting out an entering wedge or “key,” about 10 feet deep in this case, in the centre, and afterwards squaring up the sides by several blasts. In the Musconetcong heading, twelve holes were first drilled, as shown in the drawing, and marked C, A being the floor of the heading. These holes were drilled with from 1½-inch to 2¾-inch “bits,” in two rows of six, 9 feet apart on the face, and angled to meet at the bottom. They were charged with 25 lb. of No. 1 and 50 lb. of No. 2 dynamite, and fired simultaneously by electricity. The No. 1 dynamite was used in the bottom of these centre holes; in all the subsequent blasts in squaring up, No. 2 only was used.

Rock Blasting — Part 77