Connah's Quay Power Station is a 1,420 MW gas-fired power station to the west of Connah's Quay in Flintshire in North Wales. It is next to the A548, being tightly situated between the road and the south bank of the River Dee.

History

The current station is the successor to the first station in the area, a coal-fired power station, located less than a kilometre to the southwest of the current station. The old station was opened on the 16 September 1954 by Lord Citrine, the chairman of the British Electricity Authority. The station was originally planned to only be of 60 megawatts (MW), but it was realised that a larger station would be needed. The coal-fired station was built in three stages, each stage having two 30 MW generating sets, giving a total generating capacity of 180 MW. The stages were completed in 1953, 1955 and 1957. Coal was provided by train from the Point of Ayr undersea colliery. There were two unloading sidings controlled by Rockcliffe Hall signalbox. Water for the station was cooled by three hyperbolic cooling towers.

Connah's Quay Power Station

The electricity output and thermal efficiency of the station was as follows:

Connah's Quay Power Station

The station was closed in 1984 and demolished in 1992.

Connah's Quay Power Station

Since its decommission and demolition, the site of the old power station has remained undeveloped.

Gas-fired CCGT station

Construction of the new gas-fired station began in July 1993. The station was built as a turnkey project by GEC Alsthom with all principal equipment supplied by GEC Alsthom divisions. Henry Boot were sub-contracted to undertake the civil engineering and building works.

The station was completed in March 1996 and cost £580m. It was officially opened by Margaret Beckett on 4 July 1997. In June 1998, the station's visitor centre opened. The station was initially owned by Powergen, who became E.ON UK in 2004 and was transferred to Uniper in 2015. The station is currently Uniper's largest CCGT power station.

The power station is not to be confused with the Deeside Power Station, a similar CCGT power station with two chimneys situated on the north bank of the River Dee, one mile to the east of the Connah's Quay station. The two plants are separated by the Flintshire Bridge, with many electricity pylons running alongside.

Specification

It is a CCGT type power station that runs on natural gas. It is made up of four 330 MW modules - hence the four chimneys. Each module has an General Electric Frame 9FA gas turbine, a Stein Industrie heat recovery steam generator and a steam turbine; in a single-shaft layout. The gas comes via an eighteen-mile pipeline from the Point of Ayr gas terminal, where gas is received from Eni's (formerly BHP and originally owned by Denver-based Hamilton Oil) Celtic gas fields (Hamilton and Hamilton North) in Liverpool Bay via the Douglas Complex. The station opened soon after the gas from the field was first produced. The station employs around 81 people.

Gas treatment plant

The Point of Ayr terminal originally delivered per day at standard conditions of treated gas to Connah's Quay. The fuel gas requirement of power station was about ; this left a gas surplus of about per day. The quality of this gas, although adequate for use in the power station, was not suitable for delivery to the National Transmission System (NTS). Because of the high nitrogen content (8–11 mol %) the Wobbe number was too low (45.9–48.1 MJ/m3) and the total sulphur content (35 ppm) was too high. A gas treatment plant with a capacity of (for times when the power station operated at reduced capacity) was constructed at Connah's Quay to treat the gas to a quality suitable for delivery to the NTS. The plant was owned and operated by PowerGen (now E.ON UK) and started up in November 1997, the plant was built by Costain's, the capital cost of the project was £40 million.