The Affric-Beauly hydro-electric power scheme for the generation of hydro-electric power is located in the western Highlands of Scotland. It is based around Glen Strathfarrar, Glen Cannich and Glen Affric, and Strathglass further downstream.
History
There had been attempts to build a hydro-electric scheme in Glen Affric in 1929 and in 1941. Both had been promoted by the Grampian Electricity Company, but both had been defeated when the authorising bills were deposited before parliament.
The North of Scotland Hydro-Electric Board was created by the Hydro-electric Development (Scotland) Act 1943, a measure championed by the politician Tom Johnston while he was Secretary of State for Scotland. Johnston's vision was for a public body that could build hydro-electric stations throughout the Highlands. Profits made by selling bulk electricity to the Scottish lowlands would be used to fund "the economic development and social improvement of the North of Scotland." Private consumers would be offered a supply of cheap electricity, and their connection to that supply would not reflect the actual cost of its provision in remote and sparsely-populated areas.
The first two major schemes promoted by the Board had been at Loch Sloy and Tummel-Garry, but both had been the subject of fierce opposition on the grounds of amenity and fishing. In order to avoid a repetition of such opposition, the Board devised a scheme which would not fulfill the full potential of Glen Affric, but which would be more likely to obtain approval. In this they were assisted by Sir William Halcrow and Partners, covering the civil engineering aspects of the scheme, Kennedy and Donkin, covering the electrical and mechanical aspects, and James Shearer, one of three architects who advised the Board. They hoped that the scheme proposed would preserve the scenic beauty of the Glen, and would help to prevent severe flooding in the glen and in Strathglass.
The earlier schemes had envisaged raising the level of Loch Beinn a' Mheadhoinn (Loch Benevean) sufficiently that Loch Affric would have become part of one huge body of water. The new scheme would only raise the level of the loch by , which ensured that Loch Affric remained distinct, and Affric Lodge was unaffected. Instead, the level of the more remote Loch Mullardoch would be raised by , to cope with fluctuations in the volume of water stored. The scheme became the Board's Constructional Scheme No.7, when plans for it were published in August 1946. Surprisingly, there were no objections at all on the grounds of amenity or fishing, and only one minor technical objection which was resolved by negotiation. Accordingly, the scheme was approved by Parliament in February 1947.
Construction
Some preparatory work was required before work on the main scheme could begin. Two camps to house the workers were required, one at Cannich and the other at Cozac, near Mullardoch. They provided accommodation for 2,100 men, as well as offices and workshops. A number of roads and four new bridges were built, to improve access to the sites, while the road beside the River Affric and Loch Beinn a' Mheadhoin was rebuilt at a higher level, to avoid it being flooded as the level of the loch was raised.
The largest dam of the scheme is at Loch Mullardoch, at the head of Glen Cannich. At long and high from the bottom of the foundations to the crest, it proved to be the largest dam constructed by the Board. of concrete were used in its structure, and it holds back of water. The work was carried out by John Cochrane and Sons, and the dam was built in two halves, using an island in the middle of the loch to reduce the volume of material required. The dam is a mass gravity dam, and by late 1949 the north wing was nearing completion, when a financial crisis meant that the government asked the Board to reduce capital expenditure. After considering various options, they decided to reduce the height of the south wing by .
Construction of the smaller structure began in March 1950, but in February 1951 the financial crisis eased, and plans to build the south wing to its original height were drawn up. Putting a new slab of concrete over an older structure carries structural risks, and so a technique which had been used on the Mundaring Weir in Australia was used. The downstream face of the dam was covered with a concrete blanket thick, which was separated from the original dam by a slot, to allow the new concrete to set without overheating the original dam. Once adequate setting had occurred, the new concrete was bonded to the old by filling the slot with crushed aggregate and grout, and this process was finished in mid 1952.