The Strategic Environmental Assessment (SEA), is a process in Denmark for assessing the environmental effects of proposed government projects and programmes. Established in 1993 by an administrative order of Denmark's Prime Minister’s Office, this requirement was not initially enshrined in law, but was supported by a government circular which required an SEA to be carried out on “government proposals with major environmental effects”. The SEA process was limited only to government proposals and did not extend to plans and programmes. SEAs were required to focus on the impacts proposals would have on physical, ecological, cultural, health and risk factors. In 1995, the SEA requirement was extended to new parliamentary acts in addition to government proposals at the national level.
Initial administrative order
The administrative order broadly outlined four steps in the SEA process.
1. Screening – using the checklist contained in the guidance (water, air, climate, surface of the earth, soil, flora and fauna, landscape, resources, waste, historical buildings, population health, safety and transport of harmful substances) proposals that were likely to have a significant environmental impact had to be identified.
2. Scoping – the cumulative effects of a bill or policy had to be identified.
3. Assessment – analysis of the effects that had been identified as significant in the previous stages. Crucially the guidance stated that it was not possible to give an overall description, so a list of factors to be referenced were included in the guidance.
4. Report – a separate report of the environmental effects had to be included, attached to the bill that was to be put before parliament. The report had to be non-technical and easy to understand – it also had to be made available to the public.
Legal Framework
The SEA Directive (2001/42/EC) was integrated into the Danish planning system in 2004. The SEA Directive now ensures that SEA has been extended to plans and programmes, rather than just government proposals. The Act on the Environmental Assessment of Plans and Programmes (Danish SEA Act) was passed into law in May 2004 and “is strictly in accordance with the requirements of the [2001/42/EC] directive”.
The SEA Act allows the Minister for the Environment a certain amount of discretion (as the administrative order of 1993 did), with the Minister able to determine whether or not a private or publicly owned company is required to carry out a SEA on their plan or programme, when they are acting in the capacity of a public authority (for example, the provision of utilities).
It is also important to note that the SEA Act can be overruled, as long as a plan or programme complies with the procedural and substantive requirements of the SEA Directive. This helps to avoid duplication with “land use plans that have been prepared in accordance with the [Danish] Planning Act”.
Guidance Documents
Despite the integration of the SEA Directive, SEA guidance was restricted to a publication called Strategic Environmental Assessment of Bills and Other Proposals: Examples and Experience issued in 1995 by the Ministry for the Environment. New guidance was prepared in 2002, but never published due to a change in government. The 1995 guidance issues a six step approach with regards to the type of information that should be included within an SEA
Formulating the problem and describing the process of the proposal and the alternatives that have been considered Identifying the relevant environmental effects Describing the extent of the likely environmental effects Identifying mitigation measures and monitoring follow up programmes assessing and weighing the environmental effects in relation to policy objectives A statement with the summary of the main findings
In 2006, The Environment Ministry released up to date guidance that related to the SEA requirements for plans and programmes dating from 2004. Instruction number 9664 entitled 'Vejledning om miljøvurdering af planer og programmer' replaced the earlier guidance dating from 1995. The new guide was later supplemented, in 2007, by examples of SEAs that had been conducted.
SEA steps required
SEA steps that are required are defined by the SEA Act and supplemented by the guidance.
The table sets out the specific SEA process as defined by 2006 and 2007 guidance from the Danish Ministry of the Environment. The process is broadly split into nine main stages: