The Atatürk Dam (), originally the Karababa Dam, is the third largest dam in the world and it is a zoned rock-fill dam with a central core on the Euphrates River on the border of Adıyaman Province and Şanlıurfa Province in the Southeastern Anatolia Region of Turkey. Built both to generate electricity and to irrigate the plains in the region, it was renamed in honour of Mustafa Kemal Atatürk (1881–1938), the founder of the Turkish Republic. The construction began in 1983 and was completed in 1990. The dam and the hydroelectric power plant, which went into service after the upfilling of the reservoir was completed in 1992, are operated by the State Hydraulic Works (DSİ). The reservoir created behind the dam, called Atatürk Reservoir (), is the third largest in Turkey.

The dam is situated northwest of Bozova, Şanlıurfa Province, on state road D-875 from Bozova to Adıyaman. Centerpiece of the 22 dams on the Euphrates and the Tigris, which comprise the integrated, multi-sector, Southeastern Anatolia Project (, known as GAP), it is one of the world's largest dams. The Atatürk Dam, one of the five operational dams on the Euphrates as of 2008, was preceded by Keban and Karakaya dams upstream and followed by Birecik and the Karkamış dams downstream. Two more dams on the river have been under construction.

Atatürk Dam

The dam embankment is and . The hydroelectric power plant (HEPP) has a total installed power capacity of 2,400 MW and generates 8,900 GW·h electricity annually. The total cost of the dam project was about .

Atatürk Dam

The dam was depicted on the reverse of the Turkish one-million-lira banknotes of 1995–2005 and of the 1 new lira banknote of 2005–2009.

Atatürk Dam

Dam

The initial development project for the southeastern region of Turkey was presented in 1970. As the objectives for regional development have changed significantly and the ambitions have grown in the 1970s, the original plan underwent major modifications. The most important change in the project was abandoning the Middle Karababa Dam design, and adopting the design of the Atatürk Dam to increase the storage and power generation capacities of the dam.

Dolsar Engineering and ATA Construction, two prominent Turkish companies, signed for the building of the dam. The construction of the cofferdam began in 1985 and was completed in 1987. The fill work for the main dam lasted from 1987 to 1990. The Atatürk Dam, listed in international construction publications as the world's largest construction site, was completed in a world record time of around 50 months.

The rock-fill dam undergoes deformations that are regularly and systematically monitored since 1990 with different types of sensors. It is estimated that the central portion of the dam crest has settled by around since the end of the construction. Settlement of the dam crest up to has been measured since the start of the detailed geodetic monitoring in 1992. The maximum horizontal (radial) deformation measured is about .

The permeation grouting work was carried out by subcontractor Solétanche Bachy and the rehabilitation work for the post-tensioning of the dam crest with ground anchors by Vorspann System Losinger International (VSL).

Hydroelectric power plant

The HEPP of the Atatürk Dam is the biggest of a series of 19 power plants of the GAP project. It consists of eight Francis turbine and generator groups of 300 MW each, supplied by Sulzer Escher Wyss and ABB Asea Brown Boveri respectively. The up to steel pressure pipes (penstocks) with a total weight of 26.600 tons were supplied and installed by the German NOELL company (today DSD NOELL). The power plant's first two power units came on line in 1992 and it became fully operational in December 1993. The HEPP can generate 8,900 GWh of electricity annually. Its capacity makes up around one third of the total capacity of the GAP project.

During the periods of low demand for electricity, only one of the eight units of the HEPP is in operation while in times of high demand, all the eight units are in operation. Hence, depending upon the energy demand and the state of the interconnected system, the amount of water to be released from the HEPP might vary between 200 and 2,000 m3/s in one day.