Guernsey Electricity Limited (GE) is the sole commercial electricity supplier on the island of Guernsey. GE has been operating for over 100 years, moving from local generation of power from coal, and later oil, to investing in cables to connect into the grids in Jersey and France through the Channel Islands Electricity Grid.

Business model

The cable connection to France provides most of the electric energy sold in Guernsey, but the power station still needs to maintain sufficient capacity to generate power should the cable fail. There are eight oil-fired diesel engines and three oil-fired gas turbines. These include two new diesel engines, given the names "Trudy"and "Freddy", costing £15m each, which were installed in engine room "D" in March 2017.

Guernsey Electricity

Environmental and cost considerations require the maximum use of the cable link, which is limited to 60MW.

Guernsey Electricity

Minimum demand is around 23 MW, with peak demand in 2022 of 95 MW. Revenue from electricity sales in 2022 was £54.7m. 29,763 customers in 2022 340,726 MWh imported 2022 30,006 MWh generated in 2022 357,311 MWh distributed 2022 Power outages were an average of 23 minutes in 2022 In 2022 92% of electricity was imported using the cable link.

Guernsey Electricity

A retail shop is attached to the power station at North Side, Vale.

GE is governed by the Electricity (Guernsey) Law, 2001 (as amended) and is regulated by the Channel Islands Competition and Regulatory Authorities.

Undersea cables

In the mid-1970s investigations were undertaken to determine the practicality of an undersea cable. Jersey connected to France in 1984 (EDF1). No further decision was taken until 1996 when it was agreed to connect Guernsey to Jersey (GJ1) and lay a second 90 MW cable (Normandie 2) from France to Jersey, the work being completed in 2000 at a cost of £50m. The cables contain a 24 fibre optic communications cable.

A second 100 MW DC cable (GJ2) was planned to be installed, but was suspended after the existing GJ1 failed. GJ1 was replaced in 2019.

GE has invested heavily in the Channel Islands Electricity Grid, using debt to finance the investment, but losses in 2019 and 2020 as a result of the failure of the GJ1 cable requiring oil to be burnt for fuel, and the cost of the replacement GJ1, damaged finances.

The possibility of a direct cable to France designated GF1 was discussed in 2021.

Future plans

In 2023 a plan for the next 25 years recommended: A new 100 MW cable (GF1) connecting Guernsey to France Solar panels to provide around 8-10% of Guernsey's needs Offshore wind farm to supply 46-55% of electricity needs The plan received political approval in September 2023.

Estimated costs are: 2024-25 £63m for upgrading the thermal plant (current power station) and £10m for solar 2026-30 £96m for GF1 interconnector and £6m for solar 2031-35 £203m for offshore wind and £6m for solar 2036-40 £28m for hydrogen fuel cell, £63m for existing thermal plant and £6m for solar 2041-45 £6m for hydrogen fuel cell, £59m for existing thermal plant and £8m for solar 2046-50 £14m for thermal plant and £6m for solar

The price paid by consumers is expected to rise until 2030, then gradually fall.

History

Early electricity uses in Guernsey

In 1887 a dynamo was used to generate electricity for street lighting in front of Randalls Brewery in the Avenue, followed in 1897 by a water-powered first domestic installation at Le Chalet, Fermain Bay.

In 1898 Edmundsons Electricity Corporation was granted the concession to build and operate an electricity supply in Guernsey. of cables would have to be installed below ground within two years. In February 1900 150 kW could be generated from the power station at Les Amballes, St Peter Port.

Prepayment meters had to be provided that would take English or French coins. Three currencies were in circulation in Guernsey at that time. £1 Guernsey was equivalent to 19s British, and 10d Guernsey was worth 1 French franc. Units being sold at 7d for the first unit per day and 4d thereafter.

The quarry industry needed electricity for cranes, and in 1902 it was decided to build a second power station at St Sampson's; this took the generating capacity to 870 kW, with units supplied rising from 65,000 to 1.75m a year in 1910. A 2,500 volt DC cable connected the two generating centres. A battery storage system was used to provide a 24-hour service. This meant the generators only needed to operate four days a week. With 1,000 consumers by 1910, the price per unit fell to an average of 2d.