The Purple Line is a part of the Namma Metro rail system for the city of Bengaluru, Karnataka, India. As of 2023, the line is and spans 37 stations from Challaghatta in the southwest to Whitefield (Kadugodi) to the east. The Purple Line is mostly elevated, with 31 elevated stations, 5 underground stations and 1 at-grade station. The Line passes through many prime activity centers of the city including Whitefield, Krishnarajapura, MG Road, Vidhana Soudha and Majestic station, which is an interchange station between Purple and Green Lines. Phase I of the Purple Line was the first underground metro section in South India.

Construction

Purple Line sections were opened as indicated below.

Purple Line (Namma Metro)

Phase I

Civil construction work on Phase I of the line began on 15 April 2007 and was originally scheduled to be completed in 5 years. However, the project faced delays and missed several deadlines. Difficult tunnel boring conditions through a mixed geology with hard rock caused major delays. The first stretch of Purple Line (Reach 1, fully elevated) between Baiyyappanahalli and Mahatma Gandhi Road was inaugurated on 20 October 2011. Reach 2 (fully elevated) between Mysore Road and Magadi Road commenced operations on 16 November 2015. These two sections operated independently until the final section, the underground stretch between Mahatma Gandhi Road and City Railway station was opened on 30 April 2016, thus linking the previously opened stretches and completing Phase I for the Purple Line.

Purple Line (Namma Metro)

Costs for the Purple Line were estimated at 4500–5000 crore. The cost of the underground stretch alone amounted to about 1000 crores. Land acquisition for Phase I of the project cost . BMRCL secured through long-term loans and by selling bonds, while the remaining project cost was funded by Central Government and the State Government. Loans were secured from several agencies - from the Japan International Cooperation Agency (JICA), from the Housing and Urban Development Corporation Limited (HUDCO), from the Asian Development Bank (ADB), and the rest from a French lending agency. Approximately 10% of the 6500 crore was to be paid as interest by BMRCL each year. The Federation of Karnataka Chambers of Commerce and Industry (FKCCI) had estimated that interest payment alone would be . However BMRCL stated that it was not so high but "definitely more than per day".".

Purple Line (Namma Metro)

The tunnels bored using tunnel boring machines (TBMs) are located approximately 60 feet below ground level, have an outer diameter of 6.5 metres and inner diameter of 5.6 metres, and situated are 5 metres apart. Two Japanese TBMs, Helen and Margarita, were used for tunneling work of the Purple Line. Tunneling work began in May 2011 and completed in May 2014. Underground stations (City railway station, Sir M Visvesvaraya, Vidhana Soudha and Cubbon Park) were built by cut-and-cover method which required 10,000 controlled blasts using 50,000 kg of explosives of 125 gm gel nitrate capsules due to hard granite rock. Blasts were carried out daily from 6 am to 7 am from March 2011 to early 2013 (regulations restricted blasting work from being carried out at other times of the day). Preparation for a single blast took approximately 3.5 hours, with the actual duration of a blast being 5 seconds. Approximately, 20,250 truckloads of debris was excavated during construction. Kolar-based National Institute of Rock Mechanics served as consultant for blasting work. There were no injuries during the entire blasting process. A total of 2500 trees were cut down during the construction of both lines of Phase I.

Reach 1 was originally scheduled to begin operations in March 2010. After missing several deadlines, it was finally opened to the public on 20 October 2011 at 4 pm IST by Union Urban Development Minister Kamal Nath. There was an overwhelming response to the metro at the commencement of operations. As per BMRCL sources within first three days of operations, people used the mass transit system. At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. Namma Metro's first 12-day cumulative revenue was . During the first month, about 1,325,000 people traveled by metro. On average, 41,390 people took the train every day, while the average daily revenue was . BMRC earned a revenue of in its first month of operation. However, average ridership during the first six months of operation was just 24,900 after the initial euphoria. BMRC earned a total of during the same period. Namma Metro posted a profit of after almost one year of operating Reach I. BMRCL estimates that nearly 8 million passengers traveled on the system during its first year of operations.