8. =Miscellaneous Items.= At the headworks of a canal there is a permanent staff of men who work the gates and look after the works. They assist in discharge observations and in reading the gauges, and they may have to take soundings in the river to see what changes are taking place. Some one is on watch day and night and reads the gauges at frequent intervals. The officer in charge occasionally inspects the works at night without notice. Detailed rules regarding the above matters, and any others that are necessary owing to special local conditions, are drawn up. Sometimes there is difficulty in getting the staff to attend properly to the regulation of the supply in the canal at night. Probably some “tell-tale” watches would be useful. They would at least show the times at which the men concerned went to the gauges or other points.

At the headworks, and at all important regulators, a stock of concrete blocks should be kept ready for the execution of any urgent repairs.

Irrigation Works — Part 79

Regarding the ordinary maintenance work on the channels, details are given in Appendices B and C. Appendix D, reprinted from _Punjab Rivers and Works_, contains rules for watching and protecting any banks or embankments which require it.

Irrigation Works — Part 79

Silt clearances and berm cutting of channels have been mentioned in Art. 1. Special attention should be given to the accurate ranging of the centre line. Otherwise the channel may become crooked. The great defect in the earthwork ordinarily met with in the banks of canals and distributaries is that the clods are not broken. In consequence of this new banks are extremely liable to breach, and much trouble and expense result. Sometimes a dam is thrown across a new distributary, and the channel upstream of it is gradually filled with water, the bank being watched and leakages made good. The dam is then shifted to a place further down. In this way the banks are consolidated.

Irrigation Works — Part 79

When a distributary is closed for silt clearance or other work, if the head regulator has planks and a double set of grooves, it is possible to stop all leakage by filling in earth between the two sets of planks and ramming it, but otherwise it is necessary to construct an earthen dam just below the regulator. Upstream of the dam the water, owing to the leakage through the planks, gates or needles, rises to the same level as the water in the canal. Native subordinates have a remarkable aptitude for allowing such dams to break while the work in the distributary is in progress or before it is measured. Now and then the dam is wilfully cut. The remedy is to make the dam of proper strength--the top should be 8 feet wide and a foot above the water,--and to have it watched day and night.