Different plans for pile bridging are given in figs. 77 to 82. Figs. 77 to 81 show plans for temporary pile work, to be used during construction. Nothing lighter than fig. 82, ought to be permanently used. A pile bridge upon a curve may need stronger lateral bracing upon the convex, than upon the concave side of the curve; and also in running water; in which cases, such a form as fig. 81 may do good service.

(For pile-driving, and for proper dimensions, see chap. XII.)

Handbook of Railroad Construction — Part 97

207. Trestling is a system of vertical posts, and of caps and braces, used both for temporary and for permanent works; temporarily to pass a road over low ground where embankments are to be made, and permanently over deep, dry gorges, where the amount of earthwork or masonry would be too great.

Handbook of Railroad Construction — Part 97

American railroads show all sizes and arrangements of trestling, from twenty to two hundred feet high. Figs. 83 and 84 show temporary works, and fig. 85 permanent.

Handbook of Railroad Construction — Part 97

The main part of the design in trestles is to connect the several posts and caps by well-formed triangles; the equilateral being the best.

The finest example of this system of building is the Genesee high bridge, over Genesee River near Portageville, on the Buffalo and New York Railroad; built by H. C. Seymour, Esq. It is eight hundred feet long, and two hundred and thirty feet above the river. It has eight stone piers, thirty feet high, upon which are placed trestles one hundred and ninety feet high, seventy-five feet wide at base, and twenty-five at top. Upon the top of all is placed a bridge fourteen feet high. To build this viaduct was used 1,500,000 feet, board measure of timber, which covered, when standing, two hundred and fifty acres; also, sixty tons of bolts. The whole time occupied in building was but eighteen months, the whole cost being $140,000.

208. In crossing rivers or bays open to navigation, it is required from any companies building a bridge, to leave a free passage for shipping. This is done by making that part of the bridge over the channel movable; (a draw).

Draws may lift up, (being counterbalanced,) may slide back upon the fixed part of the bridge, or may turn on a pivot. Fig. 86 shows a draw much used at present, and answering every purpose. Each half of the movable part must be calculated as a small bridge. The rods _c c c_ support the overhanging part of the draw while open. The whole revolves upon a centre pin and a set of rollers.