The Thirsk and Malton line was a railway line that ran from a triangular junction on what is now the East Coast Main Line and served eight villages between Thirsk and Malton in North Yorkshire, England. The line was built after a protracted process due to inefficiencies and financial problems suffered by the then York and North Midland Railway.

The line was opened in 1853 and connected with the Malton and Driffield Junction Railway at Scarborough Road Junction just east of Malton. The entire route was initially envisaged as a through route between Hull and Glasgow, but it mostly ended up serving the local communities on the line. Express workings regularly used it between Scarborough and Newcastle, but they were reduced to a slower speed than usual because of the lower speeds on the rural lines. The line closed to passengers between Gilling and Malton in December 1930. The section from the East Coast Main Line (ECML) to Gilling was retained after closure as the branch from Gilling to Pickering did not close to passengers until 1953 with complete closure coming in 1964.

Thirsk and Malton line

History 1853–1930

Several companies were vying to build railways across Ryedale, but in 1846, the Newcastle and Darlington Junction Railway received assent from Parliament for the construction of a line towards Malton from what was the Great North of England Railway's route between York and Darlington. Several amalgamations later and construction was started in October 1851 with the Thirsk and Malton (T & M) Line opening in 1853 under the York, Newcastle and Berwick Railway. In 1854, the Y, N & B became a constituent part of the North Eastern Railway and the Thirsk and Malton railway became an asset of the NER.

Thirsk and Malton line

The branch was built with north and south facing junctions on the York, Newcastle and Berwick line (what today is known as the East Coast Main Line). Both Sessay Wood Junction (north) and Bishophouse Junction (south) had double track formations that verged eastwards and narrowed into a single line at Sunbeck Junction. Bishophouse Junction to Sunbeck Junction was not opened until 9 October 1871, when the Gilling and Pickering (G & P) route opened up to traffic.

Thirsk and Malton line

The line then proceeded in a north easterly direction towards Husthwaite Gate and Coxwold, before going due east to Ampleforth and Gilling. At Gilling there was a spur to the north for the Gilling and Pickering Line, whereas the Thirsk and Malton Line headed south eastwards through Hovingham, Slingsby, Barton-le-Street and Amotherby before crossing the York to Scarborough line on an overbridge and arriving at Scarborough Road Junction, Malton. The line was in length with a further section of from Scarborough Road Junction to Malton Station.

The line was single throughout with passing loops at Coxwold and Gilling. The place where the G & P ran north from the Thirsk and Malton line was listed as Parliamentary Junction, but in effect it was two single lines eastwards from Gilling Station which diverged without a junction. This was an economy measure meaning that the NER didn't need to install any points or employ staff to operate them. The two lines ran parallel to each other for out of Gilling Station. When the G & P was constructed, it was not necessary to obtain extra land for the formation east of Gilling to Parliamentary Junction as the original T & M proposal involved buying enough land for double track. In the end, only a single line was constructed and all bridges were built for single lines only leaving a large slice of unused land inside the railway fencing.

Trains for Malton needed to stop at Scarborough Road Junction and then reverse into Malton station using the Malton and Driffield lines. Trains for Gilling, Pilmoor and Thirsk had to do the same manoeuvre in reverse. Save for the odd excursion, summer only Filey Holiday Camp trains and stone traffic, no trains went through directly from Thirsk to Driffield. Stations on the section between Gilling and Scarborough Road Junction saw their last regular passenger trains on 30 December 1930 with official closure coming on 1 January 1931. By 1914, the services on this stretch of the line had been downgraded to run between Gilling and Malton with a connection to the Pickering to York services at Gilling Station. Four services a day operated on this section. The stations remained open for goods and it was possible to travel as a passenger from these stations on Summer Saturday's only until complete closure.