The Manchester and Bolton Railway was a railway in the historic county of Lancashire, England, connecting Salford to Bolton. It was built by the proprietors of the Manchester, Bolton and Bury Canal Navigation and Railway Company who had in 1831 converted from a canal company. The long railway was originally to have built upon most of the line of the canal, but it was eventually built alongside the Salford and Bolton arms of the canal. The Act of Parliament also allowed the construction of a connection to Bury, but technical constraints meant that it was never built.

The railway required significant earthworks, including a tunnel. The railway termini were at Salford railway station and Trinity Street station in Bolton. The railway was opened in 1838 to passenger and freight services. In 1841 it was extended to Preston, and in 1844 to Victoria railway station in Manchester. It amalgamated with the Manchester and Leeds Railway in 1846.

Manchester and Bolton Railway

The railway is in use today as part of the Manchester to Preston Line, although some of the original stations are no longer in use.

Manchester and Bolton Railway

History

Background

In the 1820s a number of proposals for a railway between Manchester and Bolton were made, some well advanced enough to be submitted to Parliament. One, in 1825, was for a line from New Bailey in Salford, to Park Field in Bolton, and included a branch line to the Mersey and Irwell Navigation. The plan included the use of an inclined plane at Clifton to allow the railway to access the higher ground from thereon. Another scheme was to connect with the planned Liverpool and Manchester Railway near Eccles, and would reach Bolton via Moorside and Farnworth. Neither of these schemes progressed beyond the early stages of planning. In 1830 two more proposals to connect the towns were made. The Manchester to Preston Railway was unsuccessful, leaving open the way for the second scheme, which would become known as the Manchester and Bolton Railway.

Manchester and Bolton Railway

Manchester, Bolton & Bury Canal Company

In 1830 the Manchester, Bolton & Bury Canal Company, led by chairman John Tobin, began to promote the construction of a railway along the line of their canal, from Salford to Bolton and Bury. Alexander Nimmo was employed to assess the proposal, and reported that it was possible "so far as he expressed himself capable of judging from his present cursory view of the canal". The shareholders then sought a bill for a railway from Bolton to Manchester and on 23 August 1831 obtained an Act of Parliament to become the "Company of Proprietors of the Manchester, Bolton and Bury Canal Navigation and Railway Company". The act authorised the abandonment of the canal between the Irwell basin and Prestolee, and empowered the company to build a line from Manchester to Bolton and Bury, "upon or near the line of ... the Canal". Two branch lines were also authorised, one from Clifton Aqueduct through to Great Lever, and the other from Giants Seat through to Radcliffe and Bury. Due mainly to the objections of local mine owners who would have lost access to the canal and therefore their supply route, and who also would not have had branch railways built for them, the company agreed to an amending bill which would keep the canal and allow the new railway to be constructed alongside it. In 1832 the company obtained an Act that allowed it to build the railway along the new alignment. The Act also allowed for an extension of the railway to New Bailey Street in Salford, and from Church Wharf (the terminus of the canal at Bolton) to Bridge Street. Smaller branches in Bolton and Salford were also allowed.

Construction of the railway started in 1833, from Salford. The company attempted to alter the route of the Bury branch, and also to extend it to Rawtenstall, but they did not receive Parliamentary approval for this. In July 1834 the committee of management applied to Parliament for "an act to amend the line of the railway between Manchester and Bolton". The amendment would take the railway along much the same course as that proposed by the Manchester to Preston Railway and was authorised by Parliament in 1835. Work proceeded so slowly that further clauses were added to the proposed act, including a continuation of the railway from Bolton, to Liverpool. Although this continuation was never built, the Liverpool and Bury Railway built such a connection in 1848. A line from Clifton to Bolton, authorised in 1835, did not materialise. The connection to Bury was never built, due mainly to the objections of the company's engineer, Jesse Hartley. The Bury branch would have required a tunnel on a gradient of 1 in 100, at the time a difficult and expensive proposition.