After the completion of the fourth cut, Fig. 32, track No. 3 is used for a car repair and extra storage track for loads or empties, for which there may not be room in tracks 1 or 2. Enough tracks have then been built for the most efficient and economical handling of the loaded material, and if the empty cars are promptly returned the steam shovel can be kept almost constantly at work. Each pit track, on which the steam shovel advances, becomes a side track on the completion of that cut, to be used as a loading track for the next cut up to the fourth cut, after which the loading tracks are taken up on completion of the cut for which they are used, Fig. 33, and relaid in the pit of the next cut, to be used, taken up, and relaid as before for the following cuts. In pits less than one-quarter mile in length, it is sometimes necessary to retain more of these tracks to provide ample storage space for all loaded and empty cars.

On all large pieces of work where the main line traffic is heavy it is important that the first side track from A to B, Fig. 32, shall be of sufficient length (usually about 700 ft.) to hold the engine and a full string of cars to avoid going on the main track when switching loads to C, and obtaining empties from D. If there is an embankment from A to B it can be widened with material taken from the cut, either by wagon or cars.

Steam Shovels and Steam Shovel Work — Part 15

Grading by this method for yard, shop and station grounds occurs mostly near large cities where better terminal facilities must be provided for. The width of the area excavated in this manner seldom exceeds 200 ft. (eight cuts) except in old gravel pits used for furnishing material for ballasting track, which are sometimes 300 ft. (twelve cuts) or more in width.

Steam Shovels and Steam Shovel Work — Part 15

Gravel pits and other wide areas excavated are seldom less than one-quarter mile or more than one mile in length. One-half to three-fourths of a mile is the most usual length; in exceptional cases two miles have been reached. Long and narrow pits can be worked more advantageously than short and wide ones.

Steam Shovels and Steam Shovel Work — Part 15

Cutting Down Grades.--For cutting down grades on railways where the traffic is not too heavy to prohibit loading on the main track, the usual plan of operations is shown in Figs. 35 to 42. The machine begins work at A, Figs. 35 and 36, the beginning point of the new grade, loading cars on the main track, cutting to the line of the new grade, and moving forward on the track on the surface of the pit as long as the height of the crane permits raising the dipper high enough over the cars to open the bottom door of the dipper and discharge its contents, B, Fig. 35. This point is usually about 2 ft. below the main track. The machine must then be gradually run upward on a cribwork of wooden blocking, generally pieces of pine 6 by 12 ins. by 4 ft. long, with some longer track stringers for supporting the sections of track on top of the blocking, and some thinner pieces for attaining exact heights of blocking when needed. As the machine moves forward the dipper still continues cutting to the line of the new grade, while the machine is gradually run upward on the blocking on a grade parallel to the grade of the main track, and slightly below it, maintaining a constant height between the top of the track on the blocking and the highest point to which the dipper can be raised on the crane to insure discharging its load on the cars. When the dipper has cut as low as the length of the dipper handle will permit, C, Fig. 35, the greatest depth to which the machine will cut below the level of the main track has been reached, and as the steam shovel advances the surface of the pit will be on a grade parallel to the grade of the main track, running upward to the summit, S, then downward, and continue so until it cuts the new grade line at H, when the dipper is made to cut on this grade, while the blocking under the machine is gradually lowered as it was previously raised, until the steam shovel reaches the end of the new grade at I, when it is again on the surface of the pit.