The engineer of the Cleveland, Mt. Vernon & Delaware R. R. gives some statements as to the cost and amount of some excavating work done under his direction. This shovel worked about 5-1/2 months in stiff clay, as follows:
March loaded 1154 cars, worked 24 days. July " 955 " " 24 " Aug. " 1157 " " 22 " Sept. loaded 1556 cars, worked 23 days. Oct. " 1552 " " 23 " Nov. " 539 " " 12 "
Total, 6,915 cars, 41,490 cu. yds. Greatest number of cars loaded in a single day, 97. Shovel supposed to work ten hours a day, but did not average more than 6-1/2 hours on account of waiting for cars. Carloads average 6 cu. yds. per car. Average cost of loading, 3 cts. per cu. yd., including expense of all men, shovel, oil, waste, etc. Loaded, hauled material, and unloaded at a distance of ten miles from pit, at 10 cts. per yd., including all costs, shovel, use of cars, engines and crews. A 20-mile haul on this road cost 15 cts. per yd., and a 30-mile haul about 20 cts. per yd., while on some roads a 30-mile haul costs over 75 cts. per yd., depending on the frequency of trains.
The following report from the superintendent of the Sioux City & Pacific Ry. gives the operations of a shovel for nine months working in a yellow clay bank from 30 to 40 ft. in length, and with a one-mile haul: "The total number of cars loaded was 31,420 in 209 days, giving an average of 150-3/4 cars per day. The greatest number of cars loaded in one day was 275, with an average of 6 cu. yds. per car. The average cost of loading per cu. yd. is 6-1/2 cts., including expense of all men about shovel, and shifting of shovel track. Average cost of unloading with one-mile haul, 7.8 cts., including wages of all men with trains and engines, use of cars and locomotives, with all supplies and repairs of same, making a total cost of 14.3 cts. per cu. yd. or 85.8 cts. per car delivered on track."
A report showing the largest amount of work, with the most complete detail as to the expense of operation was furnished by the resident engineer of the Missouri Valley & Blair Railway & Bridge Co., contractors for the Chicago & Northwestern Ry. bridge across the Missouri River at Missouri Valley, Ia., the material excavated being used in the approaches to the bridge. The work, a tabulated statement of which is given in Table IV., was done under the most favorable circumstances, with but few delays, and with but one locomotive, as the cars ran down the hill themselves while being loaded, the locomotive being employed to haul the empty cars back; the haul was short and a round trip was made in 30 minutes. The report shows that during the work of six months the average number of cars loaded per day was 205, including delays and movings, and that the average cost per cu. yd. was 7 cts., which, as shown, included labor of loading, moving shovel about once a month, moving track to suit, dynamite for caving bank, repairs of shovel, fuel, oil, waste, wages of watchman, rent of cars and locomotives, labor of engineers, firemen and wipers, labor, conductors and brakemen, and, in fact, absolutely everything connected in any way with filling the embankment.