Harmony Link is a planned submarine power cable between Lithuania and Poland. The purpose of the cable is to finish the transition of the Baltic states from IPS/UPS to the synchronous grid of Continental Europe.

History

On 21 December 2018 Lithuanian electricity grid operator Litgrid and Polish electricity grid operator PSE signed agreement in order to start planning the cable. Project given official name Harmony Link.

Harmony Link

Construction works expected to start in 2023 and finish in 2025.

Harmony Link

In June 2023 the constructions works started for Darbėnai transmission station that will serve for Harmony Link project.

Harmony Link

About the project

Harmony Link will connect the Zarnowiec substation in the Pomeranian region of Poland with the Darbenai substation in the Kretinga region of Lithuania. The key component of the interconnector is a 700 MW High Voltage Direct Current (HVDC) cable. The power link will be about 330 km long, of which about 290 km will be the offshore part.

Construction of the interconnector is expected to be completed in 2025.

Financing

The total investment planned for the Harmony Link project is around €680 million, of which €493 million will come from the Connecting Europe Facility.

See also

Energy in Lithuania

List of high-voltage transmission links in Lithuania

Electricity sector in Sweden

Baltic Cable, cable between Germany and Sweden

Konti-Skan, cable between Denmark and Sweden

Estlink, cable between Estonia and Finland

Fenno-Skan, cable between Finland and Sweden

LitPol Link, cable between Lithuania and Poland

NordBalt, subsea cable between Lithuania and Sweden

SwePol, cable between Poland and Sweden

References

External links

Litgrid

Electrical interconnectors to and from the Baltic grid

Submarine power cables

HVDC transmission lines

Electric power infrastructure in Poland

Electric power transmission systems in Lithuania

Connections across the Baltic Sea

Lithuania–Poland relations