The Herefordshire and Gloucestershire Canal (sometimes known as the Hereford and Gloucester Canal) is a canal in the west of England, which ran from Hereford to Gloucester, where it linked to the River Severn. It was opened in two phases in 1798 and 1845, and closed in 1881, when the southern section was used for the course of the Ledbury and Gloucester Railway. It is the subject of an active restoration scheme.

History

The first plans for a canal between Hereford and Gloucester were made by Robert Whitworth, one of James Brindley's pupils, in 1777. The route was part of a grander plan to Stourport-on-Severn and Leominster as well. Twelve years later, Richard Hall submitted plans for a canal via Ledbury.

Herefordshire and Gloucestershire Canal

In March 1790, the promoters decided to submit the plans to Parliament. Josiah Clowes, an engineer who had previous experience of working on the Chester Canal and who had worked with Whitworth on the Thames and Severn Canal, was to be the engineer. It appears that he re-surveyed the route, and recommended a change, so that it passed through Ledbury. A branch would be built to Newent where there were minor coalfields, and the canal would be suitable for boats , capable of carrying 35 tons. The estimated cost was £70,000, and it was expected to carry 33,203 tons per year, generating £9,582 in revenue. Some of the promoters began to think that improving the River Wye might be a better option, but the announcement of new seams of coal at Newent resulted in a decision to obtain an Act of Parliament (31 Geo. 3. c. 89), which was granted in April 1791.

Herefordshire and Gloucestershire Canal

Hugh Henshall, who was the brother-in-law of James Brindley, was asked to re-survey the route in 1792, and recommended a diversion to Newent. This route required a tunnel at Oxenhall, and another act of parliament was obtained in 1793 to sanction the new route. Josiah Clowes died in 1795, and was succeeded as engineer by Robert Whitworth. By late 1795, the initial section was open to Newent, but the tunnel was causing major problems.

Herefordshire and Gloucestershire Canal

In order to build the tunnel, twenty shafts were sunk along its route, so that there could be multiple working faces. However, there were considerable difficulties caused by the volume of water entering the shafts. Horse-powered pumps proved inadequate, and eventually steam-powered pumps were employed, but this added to the cost, and the tunnel was a large factor in the failure to complete the canal.

The canal was opened to within one mile of Ledbury in 1798, but stopped there as the cost had far exceeded the estimates. The Coal Branch to the mines at Newent was never a success, as the coal was of very poor quality, and the branch fell into disuse very quickly. The price of coal in the region dropped from 24 shillings (£1.20) per ton to 13/6 (68p) but the coal was a good quality product which travelled up the canal from the River Severn. Ledbury remained the terminus for another forty years, although a short extension to enable coal to be delivered to the Ledbury gas works was completed in 1832.

Second phase

In 1827, Stephen Ballard became the new clerk of the company, and produced a report on how to complete the canal in 1829. In 1838, he proposed a new route for the final section, but the engineer James Walker advised against it, and so in May 1839, a new Act of Parliament was obtained, allowing the company to raise the money to complete the canal. Work started on 17 November. A feeder from the River Frome to the summit level was completed in August 1842, and the canal opened in stages as it was completed, with extensions to Canon Frome wharf in January 1843, Whithington wharf in February 1844, and finally to Hereford basin on 22 May 1845.

As with the first phase, it was the tunnel construction which caused the most problems, and Ashperton tunnel, although only long, was affected by water flooding the work faces and by unstable rock, resulting in the need to construct a brick and stone lining. Again, costs escalated well beyond the original estimates.

Operation

The canal had cost far more to build than was originally planned. The whole canal had been estimated at £69,997 by Josiah Clowes in 1790, but the section to Ledbury had cost in excess of £104,000. Stephen Ballard had estimated the cost of the second phase at £53,000, but the final cost had been £141,436. With little increase in trade from the longer canal, the company tried to sell it to a railway company almost immediately, but were unsuccessful, and so tried to boost trade.