In the same manner a postscript on a letter or quotation blank is not an actual part of the contract unless it is signed.
Other members have also attempted to enforce terms printed on their invoices where such terms were not referred to in the original order or contract of sale. The following opinion will be helpful in such matters:
The question of the invoice may be settled with little difficulty. Nothing upon the invoice is binding upon the buyer, whether it is written or printed and whether it stands in the body of the document or in the margin. A contract is made by two persons, and it is binding only in so far as both have agreed to be bound by it. An invoice is made, after all the terms of the contract have been irrevocably fixed, and it is made by only one person. The seller would have things very much his own way if he could go off alone, after a contract had been made, and alter or amend or limit or explain it by his own act. He has no such power, of course, and he cannot put anything upon his invoice in writing or in print, that will bind the buyer.
INTERPRETATION OF “REASONABLE TIME,” “DUE NOTICE,” ETC.
Frequently our members ask what constitutes shipment within a reasonable time, or what is the meaning of “due notice,” etc.
The courts are always careful not to give any general definition of such words as “due,” “reasonable” and the like. What is due or reasonable notice in one case might not be so in another; and each case is made to stand on its own facts. “Due notice,” in one case or in any other, is such notice as, all of the circumstances and conditions being duly considered, would permit the person receiving the notice to do that which was required of him. Evidence is to be presented, on the one side, and on the other, to show whether due notice, within this definition, was or was not given. Due notice is sufficient notice, and that which is sufficient in one case may be too much or too little in another.
IF SHIPMENTS ARE NOT TENDERED IN TIME THE BUYER NEED NOT TAKE THEM.
Question.—In December, 1909, we placed an order for nine cars of lumber to be delivered in March, 1910. Part of the shipment was made in February and March, leaving about a third unshipped on the first of April. We wrote the sellers to cancel the order. They object to this cancellation, saying that the delay was caused by a breakdown of their mill which was unavoidable and say for this reason the order is in force, as they are ready to make delivery of the balance of the goods to-day, April 7th, one week after the contract date expired. Have we a legal right to cancel under these conditions?