The Xlinks Morocco-UK Power Project is a proposal to create 10.5 GW of renewable generation, 20 GWh of battery storage and a 3.6GW high-voltage direct current interconnector to carry solar and wind-generated electricity from the Kingdom of Morocco to the United Kingdom. Morocco has far more consistent weather, and so should provide consistent solar power even in midwinter.

If built, the cable will be the longest undersea power cable by far, and would supply up to 7.5% of the UK's electricity consumption. The first phase of the project is expected to be operational in 2029, with the second phase due in 2031.

Xlinks Morocco–UK Power Project

Current status

As of May 2022, Xlinks had secured "up to" £40million in development funding for the project, and it was reported to be close to appointing bankers to help raise the billions of pounds of investment funding required.

Xlinks Morocco–UK Power Project

Sky Business News reports that the company has "held extensive discussions with the [UK] government about its plans, which are drawing particular interest in Whitehall".

Xlinks Morocco–UK Power Project

In August 2023 Xlinks was declared a project of “national significance” by Claire Coutinho, the UK’s new energy secretary.

Power generation

Generation is proposed from a solar farm covering around , together with a wind farm of approximately , complemented by a 20GWh / 5GW battery. The planned total generating capacity is a nominal 10.5GW.

Location

The wind and solar farms will be located in the Guelmim-Oued Noun region of Morocco. The region has excellent generating characteristics: The desert location has sunshine with the third highest Global Horizontal Irradiance (GHI) in North Africa. The consistently strong winds blow from the North and North-West. Mountain ranges inland from the coast concentrate the wind and enjoy some of the highest onshore wind power densities in Africa.

Daily consistency

The PV component will generate electricity during daylight hours, and the PV panels will move to track the sun to increase output in the morning and the evening. In Morocco, the prevailing winds blow most strongly in the afternoon and early evening, driven by the temperature difference between the Sahara Desert and the cooler Atlantic Ocean. These generating characteristics, combined with battery back-up, should allow the cable to run at full capacity for approximately 20 out of each 24hours in the day.

Seasonal consistency

Because of the intense year-round sunshine, solar panels are expected to produce three times more energy than they would in the UK. The panels will generate throughout the year, including the winter months when, in Britain, sunshire is scarce and the days are short. The reliable prevailing winds will generate power consistently, even at times of low winds in Europe.

Interconnector cable

Route

If built, the undersea cable will run from landfall near Tan-Tan in southern Morocco to National Grid connection points at Alverdiscott near the north coast of Devon, England.

The cable will follow the shallow water route from Morocco to Great Britain, going to a maximum depth of . Following the continental shelf is longer than the direct route, but is less technically challenging and avoids the abyssal depths of the Bay of Biscay.

The cable route passes Spain, Portugal and France, but is not planned to have any electrical connection to these countries. This will massively simplify obtaining permits from those countries.

Technical specification

The 3.6GW interconnector is planned to consist of two independent 1.8GW circuits, each with separate positive and negative cables.

Manufacture

Xlinks proposes to manufacture the submarine power cables through a separately financed subsidiary, XLCC, and has secured manufacturing sites in Hunterston, Scotland, on Teesside and at Port Talbot in Wales, which are now "under development". As of November 2021, production is planned to start in 2024, and it will take four years to produce the cables required by the project.

Project promoter

The project developer, XLinks Ltd., is a start up, and this is its first project, but according to the Business editor of Sky News it does have a "heavyweight board".