The Hudson Project is a 345 kV AC underground and submarine power cable system which supplies electric power to New York City from the Bergen Generating Station, in Ridgefield, New Jersey. The cable system was laid by Anbaric Development Partners.

Overview

The system consists of a high-voltage direct current (HVDC) back-to-back station with a transmission rate of 660 MW and DC voltage of 180 kV at 1 Railroad Avenue () in Ridgefield, which is connected by a 230 kV line with the nearby substation. From the static inverter plant the three-phase AC line to Consolidated Edison's W. 49th Street substation at starts, is in its whole length implemented as underground or submarine cable, buried in non-navigable and in navigable sections.

Hudson Project

After travelling through the Edgewater Tunnel, the cable enters the Hudson River at Edgewater, New Jersey and runs along the eastern side of the river parallel to the shore until piers 92 and 94, where it enters Manhattan.

Hudson Project

Construction of the link started in May 2011 and was completed in June 2013.

Hudson Project

The cable was completely removed and replaced in 2017. The Ariadne, a 130-meter cable ship, performed the submarine cable replacement.

See also

Neptune Cable (submarine power cable between New Jersey and Long Island, NY)

References

External links

Master Electric Transmission Plan for NYC - 2009

Buildings and structures in Bergen County, New Jersey

Buildings and structures in Manhattan

Edgewater, New Jersey

Electric power transmission systems in the United States

Fairview, New Jersey

Hudson River

Ridgefield, New Jersey

New York City infrastructure

Electric power transmission systems in New Jersey

Submarine power cables

Port of New York and New Jersey

Consolidated Edison

Public Service Enterprise Group

Energy infrastructure completed in 2013

2013 establishments in New Jersey

2013 establishments in New York City