Diamond Valley Lake is a man-made off-stream reservoir located near Hemet, California, United States. It is one of the largest reservoirs in Southern California and one of the newest. It has a capacity of . The lake nearly doubled the area's surface water storage capacity and provides additional water supplies for drought, peak summer, and emergency needs.

The Metropolitan Water District of Southern California (MWD) began the $1.9 billion construction project in 1995. Filling of the lake, by way of the Colorado River Aqueduct, began in and was completed in . The lake is served by the Inland Feeder.

Diamond Valley Lake

The lake features three earth fill dams, two located on either side of the valley and one on the north rim. Construction of the dams used nearby materials, and was one of the largest earthworks projects in the United States. Excavation of core materials for the dams resulted in many paleontological finds, all of which are displayed at the Western Science Center at the lake's East end. The lake is open to boating and fishing, along with hiking and other recreational activities around the lake.

Diamond Valley Lake

Geography

Diamond Valley Lake is located within the Domenigoni/Diamond valleys, between the Domenigoni Mountains and Rawson Mountains, southwest of the city of Hemet. The site was chosen because of its location between the cities of San Diego and Los Angeles, and because of the raw materials located on-site for the construction of the three dams. The location was also chosen because of its proximity, about , to the existing Colorado River Aqueduct that originally supplied the lake with water.

Diamond Valley Lake

Construction

Planning for the lake began in 1987. The main goal was to meet Southern California seasonal, drought and emergency needs. MWD chose the current site because of its geographic location, and began construction planning in 1993. Construction of the lake began in 1995 with construction of the three dams. With over 40 million cubic yards of foundation excavation and 110 million cubic yards of embankment construction, the construction of the dams was the largest earthworks project in the United States.

The shovels, loaders and trucks used on the project were the largest available, and established a new standard for earth and rock movement. The two rock processing plants established for the project provided combined production exceeding the capability of any single commercial processing operation in California. Construction of the lake was the largest construction project by the MWD since building the Colorado River Aqueduct.

At its peak in 1997 and 1998, the reservoir construction project employed an average of 1,800 people. At times, more than 1,900 people labored in building the reservoir's three dams. From start to finish, about 5,000 people were employed by the construction project.

Dams

Construction of the three dams was completed in 1999, requiring the excavation of of foundation material. The earth fill dam project required about of sand, clay and rock. Much of the materials needed were obtained from the project area. Core materials were obtained from the silty and clayey sandy alluvium in the floor of the reservoir and the rock fill came from the bedrock highlands of the reservoir's south rim. Design and construction of the dams took into consideration the threat of earthquakes with the San Jacinto Fault Zone, located about from the reservoir, and the San Andreas Fault, located about from the reservoir.

West Dam

The west dam rises to above the valley floor. It spans over a nearly flat alluvial valley floor between bedrock abutment ridges. About 65% of the dam's foundation area is founded on quartzite and phyllite bedrock. The remainder is founded on dense alluvium that fills three buried channels, which are up to deep. The foundation excavations were extended below the original ground surface to remove liquefaction soils that would have made the dam unstable in an earthquake.

To minimize foundation seepage through the alluvium, thick cut-off walls of plastic concrete were constructed across the three alluvial channels and excavated at least into bedrock. To reduce seepage through the rock foundation, the entire core width was consolidation grouted and a double-line grout curtain was installed to a depth of approximately . Grouting of the west dam took about two years to complete and required of grout holes.

East Dam

The long East Dam, constructed by a Kiewit-led joint venture, is the longest of the three dams. It measures wide at the base and wide at the top. Before embankment of the dam could begin, more than of alluvium had to be excavated to reach a solid bedrock foundation.