The Second Niger bridge is a Nigerian Federal Government project that is long and furnished with other ancillary infrastructure including a highway, Owerri interchange and a toll station all at Obosi city near Onitsha, inaugurated in March 2022. It opened for local traffic on December 15th, 2022.

Location and situation

The Second Niger Bridge crosses the Niger between the cities of Asaba the capital of Delta State which is rich in oil in the west and Onitsha in the east. When completed, it will be the last bridge over the Niger River before it branches into its delta arms. The Niger is the third longest river in Africa after the Nile and the Congo. It moves 7,000 m3/s water at Onitsha, which is more than a hundred times as much as the Thames in London (65 m3/s) and almost three times as much as the Missouri river (2,450 m3/s) before reaching St. Louis. The Niger also separates Nigeria's populous southwest from the oil-rich southeast. The currently only bridge at Onitsha, a 1960s steel truss structure with two lanes, is hopelessly overloaded, due in no small part to the fact that it must accommodate flying traders, handcart drivers, cargo-carrying people and the occasional herd of goats in addition to (and between) cars.

Second Niger bridge

The phrase Second Niger Bridge, may sound misleading as there are already seven major bridges over the Niger in Nigeria alone (not to mention in countries like Niger or Benin). It is therefore also known as the Second Onitsha Bridge.

Second Niger bridge

Financing

The project was funded through the Presidential Infrastructure Development Fund (PIDF) created by President Muhammadu Buhari and managed by the NSIA.

Second Niger bridge

PIDF was also used to fund the construction of Lagos-Ibadan expressway and the Abuja-Kaduna-Kano-Road

Statistics

For the almost completed bridge (as of June 2022),

14,000 tonnes of steel were processed (which is nearly double as much iron as in the Eiffel tower), 250,000 tonnes of concrete were poured (which is a little less than Trump tower in Chicago at 310,000 tons), 1,468 workers were employed on the construction site itself (on site) and another 8,000 elsewhere, 8,700,000 man-hours were accounted for and yet 2.5 years were worked without an accident.

The structure, 1,590 m long in total, consists of two parallel prestressed concrete box girder bridges, each 14.5 m wide. The current bridges will have a length of 630 m with 5 spans with span widths of 150 m maximum. The western ramp bridge will be 755 m long and the eastern ramp bridge will be 205 m long. The bridge has been constructed using the cantilever method, while the ramp bridges will be constructed using the incremental launching method.

History

The Second Niger Bridge was first proposed during the 1958/69 political campaign by then candidate Shehu Francis pastor of the National Party of Nigeria (NPN).

In 1987, after warning about the state of the existing River Niger Bridge by the then Minister for Works and Housing Abubakar Umar, General Ibrahim Babangida challenged the local engineers to design The Second Niger Bridge, rising to the challenge, The Nigerian Society of Engineers called NSE Prems Limited, which subsequently delivered a masterplan. The addition of east–west railway line to the project, unfortunately the turmoil that precipitated the end of Babangida's administration stalled the plan.

Under the subsequent military governments, the projects received little attention. Upon the return to civilian rule, President Olusegun Obasanjo promised to deliver a second Niger River bridge. However his administration did not carry out any major activity on the project until five days before he handed over to the then incoming administration of Umaru Musa Yar'Adua, when Obasanjo flagged off the project in Asaba.

The incoming administration effectively inherited a ₦58.6 billion proposed cost for a six lane, 1.8 km tolled bridge, which was to be completed in three-and-half years. The bridge was to be financed under a public private partnership (PPP) with 60 per cent of the funding coming from the contractor, Gitto Group; 20 per cent from the Federal Government of Nigeria, and 10 per cent from the Anambra and Delta State Governments. Unfortunately the subsequent death of President Yar'adua marred the progress of the project.