Line 4 (Yellow) () is one of the six lines that make up the São Paulo Metro and one of the thirteen lines that make up the São Paulo Metropolitan Rail Transportation Network. Originally called Southeast-Southwest Line, the line goes from Vila Sônia to Luz and currently has 11 stations along its and transports around 800,000 users/day. It is one of the most modern subway lines in Latin America and the first line in the region to utilize driverless trains and platform screen doors in all stations.
Due to fiscal constraints, the construction of the line was divided into two phases: The phase one was completed in 2011 and the phase two was partially inaugurated between 2014 and 2018 and was fully completed by 2021.
Now completed, Line 4 - Yellow goes from Vila Sônia to Luz station, in a long stretch. It was expected that the line would be fully completed by 2014. However, the deadline has been repeatedly pushed back and completion was only completed on 2021. It is operated by ViaQuatro, a private company which won the public-private partnership to operate Line 4 for 30 years, which can be renewable for another 30 years. Companhia do Metropolitano de São Paulo, the company operates some other lines in the São Paulo Metro, monitors the operation of the line.
History
Conception
Conceived since the years 1940s, the route of Line 4-Yellow was present in all studies for deployment of the Metro in São Paulo since. This road was consolidated in 1968 when the initial studies for the implementation of the current subway network, receiving at that time, the name of Southeast-Southwest Line. In parable form, would connect the neighborhoods of Pinheiros and Sacomã, from Jóquei Clube station to Via Anchieta station, through the Downtown, cutting East-West line of the Metro in República and Pedro II stations. Integration platforms came to be built in those two stations, but were not used. The Republic station platforms, built in the 1980s, with a further configuration of line 4, would be demolished for the passage of the tunneling machine, equipment that built the tunnel of Line 4 between Faria Lima and Luz stations, those from Pedro II station became a depôt. The consolidation of the project was only in 1993, when the basic design was first developed, already no longer including the Southeast portion, embedded in other policies of the Metro expansion and improvement of commuter trains.
Even in the 1990s, the Metro considered taking Line 4 to Tatuapé station, with the intent to relieve the Line 3-Red. This idea was discarded, having been replaced by a possible expansion of the Line 2-Green until that section. The construction of the Expresso Tiradentes (formerly Fura-Fila), designed in the administration of mayor Celso Pitta and the first section delivered in 2007, further reinforced the intention to build Line 4 only in the vector southwest of the city, from Luz Station.
Construction
Construction was carried out in several phases, with trains initially operating from Luz to Butantã in Phase 1 with six stations, followed by five more stations and the full run from Luz to Vila Sônia in Phase 2.
On January 12, 2007, during the construction of Pinheiros station, a large part of the site's access tunnel collapsed, opening an 80 m (265 ft) diameter crater, killing seven people. Several houses and vehicles were swallowed by the hole, including a minibus; four of the victims were inside. A lot more houses suffered heavy damage, with several of these being declared condemned. Following Pinheiros' accident, Época magazine, aside Rede Globo, made a series of revelations about the security of the other line's stations, then still in building stage, dispensing special attention to the Paulista station, at Consolação quarter, a more heavily populated area, where a crater like that would have claimed a lot more lives. The line's works were kept paralysed for about two months. Because of the press' accusations, the timetable was delayed for about four months, and Pinheiros construction could only be resumed after the end of the analysis procedures designed to discover the accident's cause. The reports were delivered in August, 2008, representing a delay of almost two years on the station's works. After work on the line resumed, two teams were digging the tunnel (one from each end, planning to meet in the middle).
As the two tunnels ("Caxingui" and "Três Poderes") approached their meeting point, a horizontal error of between the two was discovered. The error was reported on 12 September 2007, and was caused by an error in topography. ViaQuatro said that there would be no delay or cost overruns due to this error.